By Polli Barnes Keller
Gulf Region North
TIKRIT — The $31.2 million rehabilitation and expansion of a 400kV/132kV substation, along with the five feeders in the Diyala Province, will provide a more reliable power source for more than 63,000 people.
Built by local construction companies with quality assurance managed by the U.S. Army Corps of Engineers, these renovations and additions will add stability to Iraq’s electrical grid. The 400kV substation – called Baghdad East - is considered to be an important component of the national electrical system, having a significant impact on the national grid.
Rehabilitating the substation not only improves the electrical distribution network in the province by reducing the load of the already overloaded substations; it also increases the reliability of the power supplies for domestic, industrial and commercial uses with less down time.
Read the Rest...
No comments:
Post a Comment